2013

2013

Sun Link Tucson Streetcar Construction Update

February 19, 2013

SunLinkIconWelcome to the City of Tucson Sun Link Streetcar Project Construction Update. If you have any questions or concerns, call the info line at 624-5656 to speak to a team member about the project.

This update is for the week of February 18, 2013.

NEW WORK ACTIVITIES

The dates and times of the scheduled work may change due to inclement weather.

  • Beginning at 6 a.m. on Monday, February 18, through 8 p.m. on Tuesday, February 19, north and southbound Sixth Avenue through traffic will be closed at the intersection of Broadway. The closure will be in place while the contractor sets the rail in concrete along Broadway.
  • One lane of eastbound travel on Broadway will be maintained.
  • Turn movements from southbound Sixth Avenue to eastbound Broadway will be permitted.
  • Turn movements from eastbound Broadway to northbound Sixth Avenue will be permitted.
  • Motorists should watch for signs directing them around the work area.
  • On Tuesday, February 19, 2013, Cushing Street between the eastbound I-10 frontage road west to Avenida Del Palo Fierro, will be closed to motorists.
  • On Tuesday, February 19, 2013 north and southbound traffic on Granada Avenue will be switched to the southbound travel lanes.
  • Access to the DeConcini Federal Court complex and the Tucson Convention Center will be maintained.
  • On Tuesday, February 19, 2013, the westbound I-10 frontage road will be reduced to one travel lane at Cushing Street while the contractor begins work to replace the water main, upgrade electrical, install track and complete paving along the roadway.
  • Travel will not be permitted along westbound Cushing Street, between Granada Avenue and the westbound I-10 frontage road.
  • Eastbound (right) turn movements from the westbound I-10 frontage road to Cushing Street will be allowed.
  • East and westbound travel on Cushing Street under I-10 will be allowed.
  • Note, as work progresses across the frontage road, for safety of the traveling public and workers in the area, the westbound I-10 frontage road will be closed to through traffic at Cushing Street. Advance notice will be given prior to the closure going into place.
  • On Tuesday, February 19, 2013, the eastbound I-10 frontage road will be reduced to one travel lane at Cushing Street while the contractor begins work to install track and complete paving along the roadway from the Louis G. Gutierrez Bridge to the eastbound frontage road.
  • East and westbound travel on Cushing Street under I-10 will be allowed.
  • On Tuesday, February 19, 2013, the contractor will place the first layer of pavement on Park Avenue, between University Boulevard and Second Street. No additional traffic restrictions are expected during this work; however, motorists should anticipate additional truck traffic in the area as haul trucks deliver paving material to the work area.
  • On Wednesday, February 20, the intersection of Congress and Fifth Avenue will be closed. The closure is to allow the contractor to install specialty rail elements within the intersection.
  • The closure will be in place until April 11, 2013 a total of seven weeks.
  • Congress Street will be closed from Toole Avenue to just west of Fifth Avenue.
  • Parking along Fifth Avenue, north and south of Congress Street will be maintained.
  • Pedestrian access around the work area will be maintained.
  • Access to Arizona Avenue from Broadway will remain open. Southbound travel on Arizona Avenue will not be permitted during this temporary closure.
  • On Wednesday, February 20, 2013 through Friday, February 22, 2013 motorists should expect night time delays or closures on Broadway, between Granada and Church Avenues. Additional details will be provided prior to the work beginning.
  • On Thursday, February 21, 2013, from 9 p.m. to 5 a.m. the following morning access to the Government Complex parking facilities on Pennington Street must be accessed from Church Avenue and Pennington Street. Officers will be on site to help direct tenants of the parking garages. This closure will be in place to allow the contractor to tie-in water service lines along Congress Street at Pennington and will be in place for one night only.

 

ONGOING WORK – ALL SECTIONS:

I-10 and West End of Line

This area of the project includes the west side of Interstate 10, Cushing Street under I-10 to Granada Avenue and Granada Avenue to Congress Street. Traffic control in this area is as follows:

  • ONGOING: The traffic signals at the intersection of Congress Street and Avenida Del Convento have been removed. This is a temporary situation, and will only be in place while the contractor installs new electrical conduit at which point the signals will be reinstalled.
  • A two-way stop will be installed in its place. This will allow Congress Street traffic a continuous flow.
  • Avenida Del Convento and traffic exiting the clinic will merge with Congress Street traffic when safe to do so.
  • The work is expected to be complete by March 15, 2013.
  • ONGOING: Traffic along eastbound Congress Street, between Avenida del Convento and the Santa Cruz River Bridge, will be shifted to the center turn lane while the contractor installs utilities and rail along the roadway. The traffic shift is expected to be in place through March 2013.
  • ONGOING: Crews are working on roadway removals and underground utilities along Avenida del Convento south of Congress Street.
  • Avenida del Convento is closed from Paseo de los Zanjeros south to Cushing Street. Turn movements from Congress Street to Avenida del Convento will be permitted.

Downtown

This area of the project includes Congress Street and Broadway through downtown from Granada Avenue to 5th Avenue. Traffic control in this area is as follows:

  • Access to the many events and activities in the downtown area can be reached from the north by using Sixth Avenue; from the east by using Broadway Boulevard or Aviation Parkway; from the south by using Euclid Avenue and turning left on Broadway; or from the west by using Congress Street and Broadway.
  • ONGOING: Congress Street, between 6th and Church Avenues is open to traffic. Motorists and bicyclists will be required to turn north or south at Church Avenue.
  • The contractor will continue work to complete sidewalk, curb, ramps and signal installation along this stretch of roadway.
  • Motorists may experience intermittent lane restriction between 9 a.m. and 4 p.m. during this work, however one lane of traffic will be maintained at all times.
  • ONGOING: Southbound Scott Avenue is closed between Broadway and Jackson Street. This closure will allow the contractor to begin preparations for rail installation along the roadway.
  • Motorists traveling south on Scott Avenue will be required to turn east at Broadway Boulevard. However, motorist may experience intermittent restrictions while the contractor installs electrical conduit across Scott Avenue north of Broadway.
  • North/southbound pedestrian access at the Broadway and Scott Avenue intersection will be re-routed around the work area.
  • ONGOING: The contractor is installing traffic signal foundations and poles along Congress Street at the intersections between Church and Scott Avenues. Motorists should be prepared for possible lane restrictions as work progresses through the area.
  • ONGOING: Congress Street between Church and Granada Avenues is closed. Work includes replacing water main, upgrading electrical, installing track and paving. A full, 24-hour street closure is in place.
  • Access to Pennington Street from eastbound Broadway will be maintained as long as possible; however, there will be short intermittent closures to allow crews to install water lines and rail across the roadway. Advance notice will be provided prior to restricting access to Pennington Street.
  • Entering Congress Street from the Pima County Complex parking garage access road will not be permitted.
  • ONGOING: Broadway between Granada and Fifth Avenues is restricted to one travel lane while the contractor completes the installation of a new water line, utilities and rail. The roadway will be open to two travel lanes during peak traffic times. The lane restrictions will be in place 24 hours a day through Spring 2013.

Fourth Avenue and University Boulevard

This area of the project includes 4th Avenue from the 4th Avenue underpass to University Boulevard, University Boulevard to Main Gate Square, and Park Avenue to 2nd Street. Traffic control in this area is as follows:

  • ONGOING: Park Avenue, between University Boulevard and Second Street, is closed while the contractor installs water line, utilities and rail.
  • ONGOING: The intersection of James E. Rogers Way and Park Avenue is open to east and west through traffic during the week, and then reclosed for the weekend. The closure allows the contractor to complete underground utility work and install rail along Park Avenue.

U of A and Health Sciences Center

This area of the project includes Second Street to Warren Avenue, the Warren Avenue underpass and a section of Helen Street that connects to the Health Science Center. Traffic control in this area is as follows:

  • ONGOING: The intersection of Warren Avenue and Second Street is closed while the contractor installs curved rail, pours the concrete track slab and paves the roadway.
  • Traffic will not be permitted through the intersection.
  • Access to residents and businesses will be maintained.
  • ONGOING: Second Street is closed to vehicular and bicycle traffic between Cherry and Warren Avenues for the removal of the existing roadway, underground utility work, rail placement and installation of the OCS.
  • Access to the Second Street Garage will be maintained.
  • ONGOING: Helen Street, between Warren and Martin Avenues is closed.
  • ONGOING: The Warren Avenue Underpass closure is expected to be in place through June 2013, while the contractor completes the removal of the existing roadway, underground utility work, rail placement and installation of the Overhead Contact System. Detour signs will be in place to help direct pedestrian and bicycle traffic through the area.

The construction activity information in this update is subject to change at any time.

Share on FacebookShare on Google+Tweet about this on TwitterShare on LinkedInPin on Pinterest