This is a special Construction Update for the Sun Link Tucson Streetcar Project. If you have any questions or concerns, SunLinkIconcall the info line at 624-5656 to speak to a team member about the project.

Downtown Lane Restrictions

  • Beginning at 8 p.m. Wednesday July 10, 2013 through the end of the day Friday, July 12, 2013, southbound Stone Avenue will be reduced to one travel lane from Pennington Street to Broadway. This temporary restriction will allow the contractor to complete paving work at the intersection of Broadway and Stone Avenue.
  • Turn movements will not be affected.
  • Motorists should consider using southbound Church or Sixth Avenues as alternate routes.